Design and Construction of Cl-9 Road as part of ICBR Works from Banga Janga Gompa (BJG) to Naga GG (NGG) between chainage Km 20.00 to Km 54.00 (net length 36.694 Km)

Salient Features:

Authority : Border Road Organization.
Authority’s Engineer : Commander, HQ 14, BRTF.
Awarded Cost : 134.53 Cr.
Appointed Date : 10th May, 2021
Schedule Completion Date : 08th May, 2024
Extended Completion Date : 04th November, 2024
Design Consultant : M/s Agnitio Infrastructure Projects Pvt. Ltd.
Proof Consultant : M/s Agnitio Infrastructure Projects Pvt. Ltd.
Safety Consultant : M/s Technocrats Infrastructure Consultants Pvt. Ltd.
Physical Progress : 38.86%
Financial Progress : 35.54%

Scope of Work:

Road Work (Flexible Pavement) : 36.694 KM.
Slab Culvert : 122 Nos.
Retaining Wall : 6780 RM.
Breast Wall : 14980 RM.
Toe Wall : 4160 RM.
Road Side Drain : 36209.8 RM.
Crash Barrier : 14883 RM