Salient Features:
Authority : National Highways & Infrastructure Development Corporation Ltd.
Authority’s Engineer : M/s Eptisa Servicios De Engenieria.
Awarded Cost : 198.00 Cr.
Appointed Date : 07th October, 2016
Schedule Completion Date : 07th October, 2019
Extended Completion Date : 05th January, 2020
Actual Completion Date : 19th December, 2019
Design Consultant : M/s NV Project Consultancy Pvt. Ltd.
Proof Consultant : M/s I. A. Futuristics.
Safety Consultant : M/s. Accrete Consulting Engineers Pvt. Ltd.
Physical Progress : 100%
Financial Progress : 100%
Scope of Work:
Road Work (Flexible Pavement) : 16.00 KM.
Box Culvert : 126 Nos.
Minor Bridge : 1 Nos. (Span 1×30)
Protection Work : 18896 RM.
Road Side Drain : 16760 RM.
Crash Barrier : 3000 RM.
Bus Bay & Bus Shelter : 4 Nos.
Junction Improvement : 1 Nos.